  • Evidence Based Scheduling – One More Way to Improve Your Estimates

    Somehow my recent discussions are mostly about estimating. Last discussion on PM Clinic happens to be on the very same subject. It reminded me about great technique which can improve your software estimates. It is called Evidence Based Scheduling and I’ve learned this from Joel Spolsky’s article.

    The basic concept is pretty simple. Jack the Developer gets the task. Actually a bunch of them. He delivers his estimates basing on his guts. Estimates are most likely crappy but at the moment it doesn’t matter much. As Jack does his work he tracks how much time he really spends on the task. It may happen it takes two days instead of planned 4-hour effort. Velocity for this task is 0,25 and it goes to the history of Jack. When Jack’s history is long enough you can use it to judge how crappy his estimates are.

    Evidence Based Scheduling uses Monte Carlo simulation which takes some effort to calculate results. However Joel brings some good news here:

    Most estimators get the scale wrong but the relative estimates right. Everything takes longer than expected. (…) This common estimator has very consistent velocities, but they’re below 1.0. For example, {0.6, 0.5, 0.6, 0.6, 0.5, 0.6, 0.7, 0.6}

    After completing a dozen of tasks you can get pretty much insight which number you should use to multiply Jack’s estimates to get something close to reality. Of course full-blown simulation will probably lead to better results but you get the idea.

    There’s one more gem in Joel’s posting which is worth stressing:

    Fix bugs as you find them, and charge the time back to the original task. You can’t schedule a single bug fix in advance, because you don’t know what bugs you’re going to have. When bugs are found in new code, charge the time to the original task that you implemented incorrectly. This will help EBS predict the time it takes to get fully debugged code, not just working code.

    I know it brings quite a lot of effort for Jack the Developer, since sometimes he fixes bugs really fast and accounting time spent on each bug fix to proper original task adds enough hassle to be reluctant to do so. However the ends are worth means this time.

    I strongly recommend you reading whole article as it delivers all the details about Evidence Based Scheduling.

  • What’s the Use of Wild Guesses Instead of Proper Estimation?

    OK, this one is controversial. Software estimating. How to do it good, or good enough? First of all, when talking about the subject we all can learn a lot from Glen Alleman who bring quite an uncommon perspective to the area as he’s based in industries which tolerate missed deadlines with much less patience than the average.

    Now, what’s the point? If you asked me how software estimating should be done I’d direct you to Steve McConnell book on the subject. Believe me or not, he didn’t write anything good (if anything at all) about role of wild guessing in software estimation. Which doesn’t make me avoiding wild guesses at all times.

    Actually sometimes I make good use of them.

    Now, go flame me.

    What’s the use of wild guesses instead of proper estimation? Wild guesses don’t have to be so wild if you ask a right person. If I ask my development manager how long something would take and it’s a piece of software he’s fairly familiar with in vast majority of cases he’ll come with some guess. It should be reasonable enough to judge whether it’d take 9 months to do the job or rather just a few weeks.

    I don’t consider that as a full-blown estimate. It’s hard to use it as a base to create a schedule but still it’s a valuable feedback to judge whether and when your team is capable to overtake the project or decide if the whole thing is worth further presales effort. If you need to develop a bunch of tools which your competitors already have in their product portfolio chances are good you won’t match their schedules and/or prices. If you add that your team is backed up for the next half of the year it’s probably not worth investing effort to do more than just getting first coarse-grained approximation.

    Yes, every wild guess should be considered very carefully since after all it’s, well, just a wild guess not an estimate done according to rules. However doing proper estimation is quite an effort and sometimes you need something rough but quick instead of exact but demanding.

    And remember: don’t ever, ever allow your wild guesses to be sent to sales department.